Skip to main content

Project Overview dashboard

Dashboard in the sidebar gives you one project's state on a single screen. Everything on it is built from the records in Execution — this is the read-and-decide view.

Use Refresh (top right) to force an immediate re-fetch.

Velora Site Pro project Dashboard showing the KPI band and work front table

KPI band

Five cards across the top. Each shows a headline number, a breakdown bar, and a small grid of counts. Clicking a number opens a drill-down; clicking a card header jumps to the matching section or tab.

CardHeadlineBreakdown
Work Front HealthTotal work frontsOn track / Behind / At risk / Not started
BlockersItems stopping work nowBlocking issues / Safety / NCRs
OverdueOverdue items + late startsOverdue issues / Late starts / Overdue actions / Critical actions
Schedule TargetsTargets achieved / total, % completeDone / Active / Behind / Not started
Progress ActivitiesTotal activities logged, date of last entryDone / Active / On hold / No target

Work front health

The same expandable RAG table as Execution's Work Fronts tab, with a legend above it.

  • Expand a row to drill through the location levels.
  • Click a work-front name for the drill-down panel: completion %, open issues, inspections, action items, sub-level breakdown, and workforce mix.

On site today

Headcount for the day with a breakdown by trade, and the change vs. yesterday.

If today's attendance hasn't been logged yet, the card shows yesterday's numbers and says so.


Blockers

Open blocking issues, oldest first, each with its age, work front, priority, and need-by date. Click one to see the WhatsApp messages behind it.


Activity feed

A rolling list of what's happened on the project — progress entries, issues, action items, and inspections.

  • Scope it to Today, 7 days, or 30 days.
  • Filter by type, or show All.
  • Click any event to open its source messages.

What's next